Office fit-out
Design and build of an office interior: design, approvals, procurement, site works, handover and the defects period.
- Fixed price
- 90 days
- 4 milestones
- 11 tasks
- 5 documents
Milestones and tasks
- Day 20Design and BOQ approved30% of the fee
- Site survey and space planDesigner
- Design, materials and BOQDesigner
- Day 55Works 50% complete30% of the fee
- Building management and authority approvalsManager
- Order long-lead itemsManager
- Day 85Handover35% of the fee
- Site worksSite Engineer
- Snag list, cleaning and handoverManager
- Day 90Defects period ends5% of the fee
- Close out defectsSite Engineer
Plus 4 sub-tasks in the app, broken down under these tasks.
Document checklist
- Signed contractFrom the client 路 day 0 路 compulsory
- Building fit-out guidelines and landlord's consentFrom the client 路 day 7 路 compulsory
- Insurance and work permitsYour team 路 day 30 路 compulsory
- As-built drawings and warrantiesYour team 路 day 85 路 compulsory
- Signed handover certificateFrom the client 路 day 85 路 compulsory